Section 21 Effect of substituting or adding new plaintiff or defendant.
(1) Where after the institution of a suit, a new plaintiff or defendant is substituted or added, the suit shall, as regards him, be deemed to have been instituted when he was so made a party:

Provided that where the court is satisfied that the omission to include a new plaintiff or defendant was due to a mistake made in good faith it may direct that the suit as regards such plaintiff or defendant shall be deemed to have been instituted on any earlier date.

(2) Nothing in sub-section (1) shall apply to a case where a party is added or substituted owing to assignment or devolution of any interest during the pendency of a suit or where a plaintiff is made a defendant or a defendant is made a plaintiff.



Section 22 Continuing breaches and torts.
In the case of a continuing breach of contract or in the case of a continuing tort, a fresh period of limitation begins to run at every moment of the time during which the breach or the tort, as the case may be, continues.
Section 23 Suits for compensation for acts not actionable without special damage.
In the case of a suit for compensation for an act which does not give rise to a cause of action unless some specific injury actually results therefrom, the period of limitation shall be computed from the time when the injury results.
Section 24 Computation of time mentioned in instruments.
All instruments shall for the purposes of this Act be deemed to be made with reference to the Gregorian calendar.
Section 25 Acquisition of easements by prescription.
(1) Where the access and use of light or air to and for any building have been peaceably enjoyed therewith as an easement, and as of right, without interruption, and for twenty years, and where any way or watercourse or the use of any water or any other easement (whether affirmative or negative) has been peaceably and openly enjoyed by any person claiming title thereto as an easement and as of right without interruption and for twenty years, the right to such access and use of light or air, way, watercourse, use of water, or other easement shall be absolute and indefeasible.

(2) Each of the said periods of twenty years shall be taken to be a period ending within two years next before the institution of the suit wherein the claim to which such period relates is contested.

(3) Where the property over which a right is claimed under sub-section (1) belongs to the Government that sub-section shall be read as if for the words "twenty years" the words "thirty years" were substituted.

Explanation.—Nothing is an interruption within the meaning of this section, unless where there is an actual discontinuance of the possession or enjoyment by reason of an obstruction by the act of some person other than the claimant, and unless such obstruction is submitted to or acquiesced in for one year after the claimant has notice thereof and of the person making or authorising the same to be made.



Section 26 Exclusion in favour of reversioner of servient tenement.
Where any land or water upon, over or from, which any easement has been enjoyed or derived has been held under or by virtue of any interest for life or in terms of years exceeding three years from the granting thereof, the time of the enjoyment of such easement during the continuance of such interest or term shall be excluded in the computation of the period twenty years in case the claim is, within three years next after the determination of such interest or term resisted by the person entitled on such determination to the said land or water.
Section 27 Extinguishment of right to property.
At the determination of the period hereby limited to any person for instituting a suit for possession of any property, his right to such property shall be extinguished.
Section 28 Repealed.
[Amendment of certain Acts.]— Rep. by Repealing and Amending Act, 1974 (56 of 1974), s. 2 and the First Schedule (w.e.f. 20-12-1974).



Section 29 Savings
(1) Nothing in this Act shall affect section 25 of the Indian Contract Act, 1872 (9 of 1872).

(2) Where any special or local law prescribes for any suit, appeal or application a period of limitation different from the period prescribed by the Schedule, the provisions of section 3 shall apply as if such period were the period prescribed by the Schedule and for the purpose of determining any period of limitation prescribed for any suit, appeal or application by any special or local law, the provisions contained in sections 4 to 24 (inclusive) shall apply only in so far as, and to the extent to which, they are not expressly excluded by such special or local law.

(3) Save as otherwise provided in any law for the time being in force with respect to marriage and divorce, nothing in this Act shall apply to any suit or other proceeding under any such law.

(4) Sections 25 and 26 and the definition of "easement" in section 2 shall not apply to cases arising in the territories to which the Indian Easements Act, 1882 (5 of 1882), may for the time being extend.



Section 30 Provision for suits, etc., for which the prescribed period is shorter than the period prescribed by the Indian Limitation Act, 1908
Notwithstanding anything contained in this Act,--

(a) any suit for which the period of limitation is shorter than the period of limitation prescribed by the Indian Limitation Act, 1908 (9 of 1908), may be instituted within a period of 1 [seven years next] after the commencement of this Act or within the period prescribed for such suit by the Indian Limitation Act, 1908 (9 of 1908), whichever period expires earlier:

2[Provided that if in respect of any such suit, the said period of seven years expires earlier than the period of limitation prescribed therefor under the Indian Limitation Act, 1908 (9 of 1908) and the said period of seven years together with so much of the period of limitation in respect of such suit under the Indian Limitation Act, 1908 (9 of 1908), as has already expired before the commencement of this Act is shorter than the period prescribed for such suit under this Act, then, the suit may be instituted within the period of limitation prescribed therefor under this Act;]

(b) any appeal or application for which the period of limitation is shorter than the period of limitation prescribed by the Indian Limitation Act, 1908 (9 of 1908), may be preferred or made within a period of ninety days next after the commencement of this Act or within the period prescribed for such appeal or application by the Indian Limitation Act, 1908, whichever period expires earlier.

STATE AMENDMENTS


Jammu and Kashmir and Ladakh (UTs).--

Insertion of Section 30A .-- After section 30, insert the following section, namely: --

"30A. Provision for suits, etc., for which the prescribed period is shorter than the period prescribed by the Limitation Act, samvat 1995.--Notwithstanding anything contained in this Act,--

(a) Any suit for which the period of limitation is shorter than the period of limitation prescribed by the Limitation Act, Samvat 1995, may be instituted within a period of one year next after the commencement of the Jammu and Kashmir Reorganisation Act, 2019 or within the period prescribed for such suit by the Limitation Act, Samvat 1995, whichever period expires earlier:

Provided that if in respect of any such suit, the said period of one year expires earlier than period of limitation prescribed therefor under the Limitation Act, Samvat 1995 (now repealed) and the said period of one year together with so much of the period of limitation in respect of such suit under the said Act, as has already expired before the commencement of the Jammu and Kashmir Reorganisation Act, 2019 is shorter than the period prescribed for such suit under the Limitation Act, 1963, then, the suit may be instituted within the period of limitation prescribed therefor under the Limitation Act, 1963;

(b) Any appeal or application for which the period of limitation is shorter than the period of limitation prescribed by the Limitation Act, Samvat 1995, may be preferred or made within a period of ninety days next after the commencement of the Jammu and Kashmir Reorganisation Act, 2019 or within the period prescribed for such appeal or application by the Limitation Act, Samvat 1995, whichever period expires earlier."

[Vide the Jammu and Kashmir Reorganization (Adaptation of Central Laws) Order, 2020, vide notification No. S.O. 1123(E) dated (18-3-2020) and Vide Union Territory of Ladakh Reorganisation (Adaptation of Central Laws) Order, 2020, notification No. S.O. 3774(E), dated (23-10-2020).]
1. Subs. by Act 10 of 1969, s. 2, for "five years" (w.e.f. 26-3-1969).

2. Ins. by s. 2, ibid. (w.e.f. 26-3-1969).

Section 31 Provisions as to barred or pending suits, etc
Nothing in this Act shall,—

(a) enable any suit, appeal or application to be instituted, preferred or made, for which the period of limitation prescribed by the Indian Limitation Act, 1908 (9 of 1908), expired before the commencement of this Act; or

(b) affect any suit, appeal or application instituted, preferred or made before, and pending at, such commencement.



Section 32 Repealed.
[Repeal.]--Rep. by Repealing and Amending Act, 1974 (56 of 1974), s. 2 and the First Schedule (w.e.f. 20-12-1974).