THE JAMMU AND KASHMIR AERIAL ROPEWAYS ACT, 2002
Administered Ministry: NO MINISTRY / Tourism
Section
Section 21 Power to close and reopen aerial ropeways.
(1) If after inspecting any aerial ropeway opened to public traffic an Inspector is of opinion that the aerial ropeway of any specified part thereof cannot be used without danger to the public or is no longer in a fit state for the carriage of any specified class of traffic, he shall state that opinion, together with the grounds therefor to the Government and the Government after such further inquiry, if any, as it may think fit, may thereupon order that, for reasons to be set forth in the order, the aerial ropeway, or the part thereof so specified, be closed to all traffic or to any specified class of traffic :
Provided that, in any case of extreme urgency, the Inspector may order the suspension of the working of the aerial ropeway or any part thereof which he considers necessary pending the orders of the Government.
(2) When under sub-section (1), an aerial ropeway or any part thereof has been closed to any traffic it shall not be reopened to such traffic until it has been inspected and its reopening sanctioned, in the prescribed manner.
Provided that, in any case of extreme urgency, the Inspector may order the suspension of the working of the aerial ropeway or any part thereof which he considers necessary pending the orders of the Government.
(2) When under sub-section (1), an aerial ropeway or any part thereof has been closed to any traffic it shall not be reopened to such traffic until it has been inspected and its reopening sanctioned, in the prescribed manner.
Section 22 Cessation of powers of promoter on discontinuance of aerial ropeway.
If at any time after the opening of an aerial ropeway, it is proved to the satisfaction of the Government that the promoter has discontinued the working of the aerial ropeway or of any part thereof, without a reason sufficient, in the opinion of the Government, to warrant such discontinuance, the Government may, if it thinks fit, declare, by notification in the Government Gazette, that the powers of the promoter in respect of such aerial ropeway or part thereof shall, from such date as it may determine, be at an end, and thereupon the said powers shall cease and determine.
Explanation :—The working of an aerial ropeway shall be deemed to have been discontinued if it has ceased for the period determined in the order published under section 7, or if the period has not been so determined, for a period of three months.
Explanation :—The working of an aerial ropeway shall be deemed to have been discontinued if it has ceased for the period determined in the order published under section 7, or if the period has not been so determined, for a period of three months.
Section 23 Powers of Government to remove aerial ropeway on cessation of promoter’s powers.
(1) When a declaration has been made by the Government under section 22 in respect of any aerial ropeway or of any part thereof, an officer appointed in that behalf by the Government may, at any time after the expiration of two months from the date determined as aforesaid, remove such aerial ropeway or part thereof, as the case be, and the promoter shall pay to the officer so appointed such costs of removal, as shall be certified by that officer to have been incurred by him.
(2) If the promoter fails to pay the amount of costs so certified within one month after the delivery to him of the certificate or, of a copy thereof, such officer may, either by public auction or private sale, and without any previous notice to the promoter and without prejudice to any other remedy which he may have for the recovery of the said amount, sell and dispose of the materials of the aerial ropeway or part thereof so removed ; and may out of the proceeds of the sale, pay and reimburse to himself the amount of costs certified as aforesaid and the costs of the sale, and shall pay over the residue (if any) of such proceeds to the promoter.
(2) If the promoter fails to pay the amount of costs so certified within one month after the delivery to him of the certificate or, of a copy thereof, such officer may, either by public auction or private sale, and without any previous notice to the promoter and without prejudice to any other remedy which he may have for the recovery of the said amount, sell and dispose of the materials of the aerial ropeway or part thereof so removed ; and may out of the proceeds of the sale, pay and reimburse to himself the amount of costs certified as aforesaid and the costs of the sale, and shall pay over the residue (if any) of such proceeds to the promoter.
Section 24 Power of Government and local authorities to purshase aerial ropeways.
(1) Where the promoter is the Government, it may at any time transfer the undertaking or any part thereof to :––
(a) a local authority or local authorities under terms and conditions approved by it with the consent of such authority or authorities ; or
(b) to any other person under such terms and conditions as may be mutually agreed upon between the Government and the transferee.
(2) Where the promoter is not the Government, the Government may,––
(a) within such limits of time and upon such terms and conditions as may be specified in this behalf in the order ; or
(b) if a time was not specified in the order, then within six months after the expiration of a period of twenty-one years from the date of the order, and within six months after the expiration of every subsequent period of seven years ; or
(c) within two months after the publication of a notification under section 22 or within six months after the publication of a notification under section 26 ;
by notice in writing require the promoter to sell to the Government or to a local authority the aerial ropeway or a part thereof, and thereupon the promoter shall sell the same upon the terms specified in the order, or if the terms were not specified in the order, then upon the terms of receiving the then value of the aerial ropeway or of the part thereof. The then value of the aerial ropeway, shall be deemed to be twenty-five times the amount of the average yearly net earnings derived by the promoter from the aerial ropeway or part thereof, during the three years immediately preceding the date of sale :
Provided that if the terms were not specified in the order published under section 7, the total amount so payable to the promoter shall not exceed by more than twenty per cent the total capital expenditure of the promoter on the aerial ropeway, or part thereof.
(3) A requisition shall not be made under sub-section (2) requiring the promoter to sell to the local authority unless the making thereof has been approved by the local authority.
(4) When a sale has been made under this section, all the rights, powers and authorities of the promoter in respect of the undertaking or part thereof sold, or, where a notification has been published under section 22 or section 26, all the rights, powers and authorities of the promoter previous to the publication of the notification in respect of the undertaking or part thereof sold, shall be transferred to the authorities to whom the undertaking or part thereof has been sold, and shall vest in and may be exercised by, that authority in the same manner as if the aerial ropeway had been constructed by it under an order made under this Act.
(5) Subject to, and in accordance with the preceding provisions of this section, two or more persons or firms may purchase an undertaking or part thereof.
(6) Where a purchase has been affected under sub-section (1) or sub-section (5),––
(a) the undertaking shall vest in the purchaser free from any debts, mortgages or similar obligation of the promoter or attaching to the undertaking :
Provided that any such debts, mortgages or similar obligations shall attach to the purchase money in substitution for the undertaking ; and
(b) save as aforesaid, the order published under section 7 shall remain in full force and the purchase shall be deemed to be the promoter :
Provided that where the Government elects to purchase; the order under section 7 shall after purchase, in so far as the Government is concerned, cease to have any further operation.
(7) Not less than two years notice in writing of any election to purchase under clause (a) or clause (b) of sub-section (2) of this section shall be served upon the promoter by the Government or the local authority, as the case may be.
(8) Notwithstanding anything hereinbefore contained, a local authority may, with the previous sanction of the Government, waive its option to purchase and enter into an agreement with the promoter for the working by him of the undertaking until the expiration of the next subsequent period mentioned in the order referred to in clause (b) of subsection (2) upon such terms and conditions as may be stated in the agreement.
(a) a local authority or local authorities under terms and conditions approved by it with the consent of such authority or authorities ; or
(b) to any other person under such terms and conditions as may be mutually agreed upon between the Government and the transferee.
(2) Where the promoter is not the Government, the Government may,––
(a) within such limits of time and upon such terms and conditions as may be specified in this behalf in the order ; or
(b) if a time was not specified in the order, then within six months after the expiration of a period of twenty-one years from the date of the order, and within six months after the expiration of every subsequent period of seven years ; or
(c) within two months after the publication of a notification under section 22 or within six months after the publication of a notification under section 26 ;
by notice in writing require the promoter to sell to the Government or to a local authority the aerial ropeway or a part thereof, and thereupon the promoter shall sell the same upon the terms specified in the order, or if the terms were not specified in the order, then upon the terms of receiving the then value of the aerial ropeway or of the part thereof. The then value of the aerial ropeway, shall be deemed to be twenty-five times the amount of the average yearly net earnings derived by the promoter from the aerial ropeway or part thereof, during the three years immediately preceding the date of sale :
Provided that if the terms were not specified in the order published under section 7, the total amount so payable to the promoter shall not exceed by more than twenty per cent the total capital expenditure of the promoter on the aerial ropeway, or part thereof.
(3) A requisition shall not be made under sub-section (2) requiring the promoter to sell to the local authority unless the making thereof has been approved by the local authority.
(4) When a sale has been made under this section, all the rights, powers and authorities of the promoter in respect of the undertaking or part thereof sold, or, where a notification has been published under section 22 or section 26, all the rights, powers and authorities of the promoter previous to the publication of the notification in respect of the undertaking or part thereof sold, shall be transferred to the authorities to whom the undertaking or part thereof has been sold, and shall vest in and may be exercised by, that authority in the same manner as if the aerial ropeway had been constructed by it under an order made under this Act.
(5) Subject to, and in accordance with the preceding provisions of this section, two or more persons or firms may purchase an undertaking or part thereof.
(6) Where a purchase has been affected under sub-section (1) or sub-section (5),––
(a) the undertaking shall vest in the purchaser free from any debts, mortgages or similar obligation of the promoter or attaching to the undertaking :
Provided that any such debts, mortgages or similar obligations shall attach to the purchase money in substitution for the undertaking ; and
(b) save as aforesaid, the order published under section 7 shall remain in full force and the purchase shall be deemed to be the promoter :
Provided that where the Government elects to purchase; the order under section 7 shall after purchase, in so far as the Government is concerned, cease to have any further operation.
(7) Not less than two years notice in writing of any election to purchase under clause (a) or clause (b) of sub-section (2) of this section shall be served upon the promoter by the Government or the local authority, as the case may be.
(8) Notwithstanding anything hereinbefore contained, a local authority may, with the previous sanction of the Government, waive its option to purchase and enter into an agreement with the promoter for the working by him of the undertaking until the expiration of the next subsequent period mentioned in the order referred to in clause (b) of subsection (2) upon such terms and conditions as may be stated in the agreement.
Section 25 Power of promoter to sell when option to purchase not exercised and revoked by consent.
Where, on the expiration of any of the periods referred to in section 24 neither the Government nor local authority purchases the undertaking and the order published under section 7 is on the application or with the consent of the promoter revoked, the promoter shall have the option of disposing of all lands, buildings, works, materials, plants and apparatus belonging to the undertaking in such manner as he may think fit.
Section 26 Proceedings in case of inability or insolvency of promoter.
(1) If, at any time, after the opening of an aerial ropeway, it appears to the Government that the promoter is insolvent or is unable to maintain the aerial ropeway or to work the same with advantage to the public, or at all, the Government may, after considering any statement which the promoter may desire to make, and after such enquiry as it deems necessary, declare by notification in the Government Gazette that the powers of the promoter in respect of such aerial ropeway, shall, at the expiration of six months from the date of such declaration, be at an end, and thereupon the said powers shall, at the expiration of that period, cease and determine.
(2) At any time after the expiration of the said period of six months, an officer appointed by the Government in that behalf, may remove the aerial ropeway in the same manner and subject to the same provisions as to the payment of costs and to the same remedy for the recovery thereof in every respect as in cases of removal under section 23.
(2) At any time after the expiration of the said period of six months, an officer appointed by the Government in that behalf, may remove the aerial ropeway in the same manner and subject to the same provisions as to the payment of costs and to the same remedy for the recovery thereof in every respect as in cases of removal under section 23.
Section 27 Power of promoter to make bye-laws.
(1) A promoter shall, subject to the provisions of sub-section (3), make bye-laws consistent with this Act,––
(a) for regulating the speed at which carriers are to be moved or propelled ;
(b) for declaring what shall be deemed to be dangerous or offensive goods and for regulating the carriage of such goods ;
(c) for regulating the maximum number of passengers and animals and the maximum weight of goods to be carried in each carrier ;
(d) for regulating the use of steam power or any other mechanical power or electrical power on the aerial ropeway ;
(e) for regulating the conduct of the promoter’s servants ;
(f) for regulating the terms and conditions on which the promoter will warehouse or retain goods at any station on behalf of the consignee or owner of such goods ; and
(g) generally for regulating the travelling upon and the use, working and management of the aerial ropeway.
(2) Such bye-laws may provide that any person who contravenes the provisions of any of them shall be liable to fine which may extend to any sum not exceeding fifty rupees and that in the case of a breach of a bye-law made under clause (c) of sub-section (1), the promoter’s servants responsible for the same shall forfeit a sum not exceeding one month’s pay, which sum may be deducted by the promoter from his pay. (3) A bye-law made under this section shall not take effect until it has been confirmed by the Government and published in the Government Gazette :
Provided that no such bye-law shall be so confirmed until it has been previously published by the promoter in such manner as may be prescribed.
(a) for regulating the speed at which carriers are to be moved or propelled ;
(b) for declaring what shall be deemed to be dangerous or offensive goods and for regulating the carriage of such goods ;
(c) for regulating the maximum number of passengers and animals and the maximum weight of goods to be carried in each carrier ;
(d) for regulating the use of steam power or any other mechanical power or electrical power on the aerial ropeway ;
(e) for regulating the conduct of the promoter’s servants ;
(f) for regulating the terms and conditions on which the promoter will warehouse or retain goods at any station on behalf of the consignee or owner of such goods ; and
(g) generally for regulating the travelling upon and the use, working and management of the aerial ropeway.
(2) Such bye-laws may provide that any person who contravenes the provisions of any of them shall be liable to fine which may extend to any sum not exceeding fifty rupees and that in the case of a breach of a bye-law made under clause (c) of sub-section (1), the promoter’s servants responsible for the same shall forfeit a sum not exceeding one month’s pay, which sum may be deducted by the promoter from his pay. (3) A bye-law made under this section shall not take effect until it has been confirmed by the Government and published in the Government Gazette :
Provided that no such bye-law shall be so confirmed until it has been previously published by the promoter in such manner as may be prescribed.
Section 28 Returns.
A promoter shall in respect of the aerial ropeway, submit to the Government returns of capital and revenue expenditure, receipts and traffic at such intervals and in such form, as may be prescribed.
Section 29 Protection of roads, railways, tramways and waterways.
No promoter shall, in the course of the construction, repair, working or management of an aerial ropeway, cause any permanent injury to any public road, railway, tramway or waterway, or obstruct or interfere with, otherwise than temporarily as may be necessary, the traffic on any public road, railway, tramway or waterway.
Section 30 Acquisition of land on behalf of a promoter.
The Government may if it thinks fit, subject to the provisions of this Act, on the application of any promoter desirous of obtaining any land for the purpose of constructing, executing, working or managing an aerial ropeway, acquire on his behalf such land under the provisions of 1[The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013(30 of 2013)], whether the said promoter is or is not a company as defined in the said Act.
1. Substituted for “Part VII of the State Land Acquisition Act, Samvat 1990” vide S.O. 3808 (E) of 2020 dated 26.10.2020.
Section 31 Notification of claims to refund of overcharges and compensation for losses.
No person shall be entitled to a refund of an overcharge in respect of animals or goods carried by an aerial ropeway or to compensation for the loss, destruction or deterioration of animals or goods delivered to be so carried, unless his claim to the refund or compensation has been preferred in writing by him or on his behalf to the promoter within six months from the date of the delivery of the animals or goods for carriage by the aerial ropeway.
Section 32 Power of the Government to make rules.
(1) The Government may, after previous publication make rules to carry out the purposes of this Act.
(2) In particular, and without prejudice to the generality of the foregoing power, such rules may prescribe––
(a) the powers and duties of an Inspector appointed under section 11 ;
(b) the accidents of which notice shall be given to the Government and to the Inspector ;
(c) the duties of the promoter’s servants and of police officers, and magistrate, on the occurrence of an accident ;
(d) the maximum and minimum rates for various classes of goods which a promoter may fix under section 18 ;
(e) the standard dimensions and specifications to which the aerial ropeway is to conform ;
(f) the manner of previous publication of bye-laws made under section 27 ;
(g) the intervals at which a promoter shall submit returns under section 28 and the forms in which such returns shall be submitted ;
(h) the manner in which notices under this Act shall be served ;
(i) the manner in which and the conditions under which, booking of goods may be permitted between an aerial ropeway and railway, tramway or another aerial ropeway ;
(j) the safe and efficient working of aerial ropeway ;
(k) the conditions under which, and the manner in which the powers conferred on promoters by section 14 and section 15 may be exercised ;
(l) the procedure for the disposal of applications under subsection (2) of section 21 to reopen an aerial ropeway or part thereof and conditions under which such aerial ropeway may be reopened ;
(m) the preparation, submission and auditing of the accounts of the promoter ;
(n) the method of arbitration for the settlement of disputes ;
(o) the fees to be charged to promoters and other persons in respect of licences, applications, enquiries, inspection and services rendered under this Act ; and
(p) the procedure for making, hearing and disposing of applications under this Act.
(3) All rules made under this section shall be published in the Government Gazette.
(4) Every rule made under this Act shall be laid, as soon as may be after it is made, before 1[Legislature of Union territory of Jammu and Kashmir] while it is in session for a total period of not less than thirty days which may be comprised in one session or in two or more successive sessions and if, before the expiry of the session in which it is so laid or the session immediately following, 2[Legislative Assembly of Union territory of Jammu and Kashmir] agree in making any modification in the rule or decides that the rule should not be made, the rule shall thereafter have effect only in such modified form or be of no effect as the case may be, so, however, that any such modification or amendment shall be without prejudice to the validity of anything previously done under that rule.
(2) In particular, and without prejudice to the generality of the foregoing power, such rules may prescribe––
(a) the powers and duties of an Inspector appointed under section 11 ;
(b) the accidents of which notice shall be given to the Government and to the Inspector ;
(c) the duties of the promoter’s servants and of police officers, and magistrate, on the occurrence of an accident ;
(d) the maximum and minimum rates for various classes of goods which a promoter may fix under section 18 ;
(e) the standard dimensions and specifications to which the aerial ropeway is to conform ;
(f) the manner of previous publication of bye-laws made under section 27 ;
(g) the intervals at which a promoter shall submit returns under section 28 and the forms in which such returns shall be submitted ;
(h) the manner in which notices under this Act shall be served ;
(i) the manner in which and the conditions under which, booking of goods may be permitted between an aerial ropeway and railway, tramway or another aerial ropeway ;
(j) the safe and efficient working of aerial ropeway ;
(k) the conditions under which, and the manner in which the powers conferred on promoters by section 14 and section 15 may be exercised ;
(l) the procedure for the disposal of applications under subsection (2) of section 21 to reopen an aerial ropeway or part thereof and conditions under which such aerial ropeway may be reopened ;
(m) the preparation, submission and auditing of the accounts of the promoter ;
(n) the method of arbitration for the settlement of disputes ;
(o) the fees to be charged to promoters and other persons in respect of licences, applications, enquiries, inspection and services rendered under this Act ; and
(p) the procedure for making, hearing and disposing of applications under this Act.
(3) All rules made under this section shall be published in the Government Gazette.
(4) Every rule made under this Act shall be laid, as soon as may be after it is made, before 1[Legislature of Union territory of Jammu and Kashmir] while it is in session for a total period of not less than thirty days which may be comprised in one session or in two or more successive sessions and if, before the expiry of the session in which it is so laid or the session immediately following, 2[Legislative Assembly of Union territory of Jammu and Kashmir] agree in making any modification in the rule or decides that the rule should not be made, the rule shall thereafter have effect only in such modified form or be of no effect as the case may be, so, however, that any such modification or amendment shall be without prejudice to the validity of anything previously done under that rule.
1. Substituted for “each House of the State Legislature” vide S.O. 3808 (E) of 2020 dated 26.10.2020.
2. Substituted for “both Houses” ibid.
2. Substituted for “both Houses” ibid.
Section 33 Failure of promoter to comply with Act.
If a promoter––
(a) constructs or maintains an aerial ropeway otherwise than in accordance with the terms of an order made under section 7 ; or
(b) opens an aerial ropeway or permits it to be opened in contravention of any of the provisions of section 10 ; or
(c) fails to comply with the provisions of section 13 ; or
(d) fails to pay within a reasonable time any compensation awarded by the Collector or by the Government under sections 14, 15, 16 or 17 ; or
(e) contravenes any of the provisions of section 19 ; or
(f) fails to send notice of any accident as required by section 20 ; or
(g) fails to close an aerial ropeway in accordance with an order passed under sub-section (1) of section 21 or reopens any aerial ropeway in contravention of sub-section (2) of that section ; or
(h) continues to exercise the powers of a promoter in respect of any aerial ropeway in contravention of the provisions of section 22 or section 26 ; or
(i) fails to comply with the provisions of section 27 or section 28 ; or
(j) contravenes the provision of section 29 ; or
(k) contravenes the provisions of any rule made under section 32,
he shall, without prejudice to the enforcement of specific performance of the requirements of this Act, or of any other remedy which may be obtained against him, be punishable with fine which may extend to five thousand rupees, and in the case of a continuing offence, to a further fine which may extend to one hundred rupees for every day after the date of the first conviction during which the offender is proved to have persisted in the offence.
(a) constructs or maintains an aerial ropeway otherwise than in accordance with the terms of an order made under section 7 ; or
(b) opens an aerial ropeway or permits it to be opened in contravention of any of the provisions of section 10 ; or
(c) fails to comply with the provisions of section 13 ; or
(d) fails to pay within a reasonable time any compensation awarded by the Collector or by the Government under sections 14, 15, 16 or 17 ; or
(e) contravenes any of the provisions of section 19 ; or
(f) fails to send notice of any accident as required by section 20 ; or
(g) fails to close an aerial ropeway in accordance with an order passed under sub-section (1) of section 21 or reopens any aerial ropeway in contravention of sub-section (2) of that section ; or
(h) continues to exercise the powers of a promoter in respect of any aerial ropeway in contravention of the provisions of section 22 or section 26 ; or
(i) fails to comply with the provisions of section 27 or section 28 ; or
(j) contravenes the provision of section 29 ; or
(k) contravenes the provisions of any rule made under section 32,
he shall, without prejudice to the enforcement of specific performance of the requirements of this Act, or of any other remedy which may be obtained against him, be punishable with fine which may extend to five thousand rupees, and in the case of a continuing offence, to a further fine which may extend to one hundred rupees for every day after the date of the first conviction during which the offender is proved to have persisted in the offence.
Section 34 Unlawfully obstructing promoter’s servant in discharge of his duty.
If a person, without lawful excuse, the burden of proving which shall lie upon him, wilfully obstructs or impedes any servant of a promoter in the discharge of his duty, he shall be punishable with fine which may extend to 1[five thousand rupees].
1. Substituted for “one thousand rupees” vide S.O. 3808 (E) of 2020 dated 26.10.2020.
Section 35 Unlawfully interfering with aerial ropeway.
If any person without lawful excuse, the burden of proving which shall lie upon him, wilfully does any of the following things, namely––
(a) interferes with, removes or alters any part of an aerial ropeway or of the works connected therewith ;
(b) does anything in such manner as to obstruct any carrier travelling on an aerial ropeway ; or
(c) attempts to do or abets, within the meaning of the 1[Indian Penal Code (45 of 1860)], the doing of any thing mentioned in clause (a) or clause (b) ;
he shall, without prejudice to any other remedy which may be obtained against him in a civil court, be punishable with fine which may extend to two thousand rupees.
(a) interferes with, removes or alters any part of an aerial ropeway or of the works connected therewith ;
(b) does anything in such manner as to obstruct any carrier travelling on an aerial ropeway ; or
(c) attempts to do or abets, within the meaning of the 1[Indian Penal Code (45 of 1860)], the doing of any thing mentioned in clause (a) or clause (b) ;
he shall, without prejudice to any other remedy which may be obtained against him in a civil court, be punishable with fine which may extend to two thousand rupees.
1. Substituted for “State Ranbir Penal Code, Samvat 1989”vide S.O. 3808 (E) of 2020 dated 26.10.2020.
Section 36 Punishments for acts of attempts tending to endanger safety of persons travelling or being upon aerial ropeway.
If any person does anything mentioned in clause (a), clause (b) or clause (c) of section 35 or does, attempts to do, or abets, within the meaning of the 1[Indian Penal Code (45 of 1860)], the doing of any other act or thing in relation to an aerial ropeway with intent, or with knowledge that he is likely to endanger the safety of any person travelling or being upon the aerial ropeway, he shall be punishable with imprisonment for a term which may extend to fourteen years and with fine which may extend to ten thousand rupees.
1. Substituted for “State Ranbir Penal Code, Samvat 1989”vide S.O. 3808 (E) of 2020 dated 26.10.2020.
Section 37 Arrest for offence against certain sections and procedure thereupon.
(1) If any person commits any offence under section 34 or section 35 which obstruct the working of an aerial ropeway or commits any offence punishable with imprisonment under section 36, he may be arrested without warrant or other written authority by any servant of the promoter or by any police officer or by other person whom such servants or officer may call to his aid.
(2) A person so arrested shall, with the least possible delay, be taken before magistrate having authority to try or to commit him for trial.
(2) A person so arrested shall, with the least possible delay, be taken before magistrate having authority to try or to commit him for trial.