Section 22-AX Penalty for Removal of any Mark.
If any person removes any mark set up for the purpose of indicating any level, boundary line or direction necessary to the execution of works authorized under this Chapter, he shall, on conviction, be punished with imprisonment for a term which may extend to three months or with fine, which shall not be less than five thousand rupees, but may extend to ten thousand rupees.
Section 22-AY Penalty for Obstruction of the Lawful Exercise of any Power.
Any person, who obstructs the lawful exercise of any power conferred by or under this Chapter shall, on conviction, be punished with fine, which shall not be less than five thousand rupees, but may extend to ten thousand rupees.
Section 22-AZ Power to make Rules.
(1) The Government, after consultation with the Corporation in regard to matters concerning it, may, by notification in the Government Gazette, make rules to carry out the purposes of this Chapter :
Provided that, consultation with the Corporation shall not be necessary on the first occasion of the making of rules under this section, but the Government shall take into consideration any suggestions which the Corporation may make in relation to amendment of such rules after they are made.
(2) In particular and without prejudice to the generality, of the foregoing power such rules may provide for all matters expressly required or allowed by this Chapter to be prescribed by rules and fees which may be charged by the Corporation.
(3) All rules made under this section shall be laid for not less than thirty days before the Legislature as soon as possible after they are made and shall be subject to rescission by the Legislature, or to such modification as the Legislature may make, during the session in which they are so laid, or the session immediate following.
(4) Any rescission or modification so made by the Legislature shall be published in the Government Gazette and shall thereupon take effect.
Provided that, consultation with the Corporation shall not be necessary on the first occasion of the making of rules under this section, but the Government shall take into consideration any suggestions which the Corporation may make in relation to amendment of such rules after they are made.
(2) In particular and without prejudice to the generality, of the foregoing power such rules may provide for all matters expressly required or allowed by this Chapter to be prescribed by rules and fees which may be charged by the Corporation.
(3) All rules made under this section shall be laid for not less than thirty days before the Legislature as soon as possible after they are made and shall be subject to rescission by the Legislature, or to such modification as the Legislature may make, during the session in which they are so laid, or the session immediate following.
(4) Any rescission or modification so made by the Legislature shall be published in the Government Gazette and shall thereupon take effect.
Section 22-AAA Power to make Regulations.
(1) The Corporation may, with the previous approval of the State Government make regulations consistent with this Act and the rules made there under, and to carry out the purposes of this Act.
(2) In particular and without prejudice to the generality of the foregoing power such regulations may provide for all matters expressly required or allowed by this Act to be provided by regulations.
(3) All rules made under this section shall be published in the Official Gazette and shall be laid for not less than thirty days before the State Legislature as soon as possible after they are made, and shall be subject to rescission by the Legislature, or to such modification as the Legislature may make, during the session in which they are so laid, or the session immediately following.
(4) Any rescission or modification so made by the State Legislature shall be published in the Official Gazette and shall thereupon take effect.
(2) In particular and without prejudice to the generality of the foregoing power such regulations may provide for all matters expressly required or allowed by this Act to be provided by regulations.
(3) All rules made under this section shall be published in the Official Gazette and shall be laid for not less than thirty days before the State Legislature as soon as possible after they are made, and shall be subject to rescission by the Legislature, or to such modification as the Legislature may make, during the session in which they are so laid, or the session immediately following.
(4) Any rescission or modification so made by the State Legislature shall be published in the Official Gazette and shall thereupon take effect.
Section 22-AAB Act done in good faith.
No suit, prosecution or other legal proceedings shall lie against any person for anything which is in good faith done or intended to be done under this Chapter or any rule or regulation made there under.
Section 22-AAC Requirement of prior notice for filing of Suit.
(1) No person shall commence any suit against the Corporation or against any officer or servant of the Corporation or any person acting under the orders of the Corporation for anything done or purporting to have been done in pursuance of this Chapter, without giving to the Corporation, officer or servant or person, as the case may be, two months’ previous notice in writing of the intended suit and of the cause thereof, not after six months from the date of the act complained of.
(2) In the case of any such suit for damages if tender of sufficient amount shall have been made before the action was brought, the plaintiff shall not recover more than the amounts so tendered and shall pay all costs incurred by the defendant after such tender.
(2) In the case of any such suit for damages if tender of sufficient amount shall have been made before the action was brought, the plaintiff shall not recover more than the amounts so tendered and shall pay all costs incurred by the defendant after such tender.
Section 22-AAD Public Servants.
All Directors, officers and servants of the Corporation shall, when acting “or purporting to act in pursuance of any of the provisions of this Chapter be deemed to be public servants within the meaning of section 21 of the Indian Penal Code (45 of 1860).
Section 22-AAE Overriding effect.
The provisions of this Chapter shall have effect notwithstanding anything inconsistent therewith contained in any other law.
Section 22-AAF Power to remove difficulties.
If any doubt or difficulty arises in giving effect to the provisions of this Chapter the Government may, by order, make provision or give such direction not in consistent with the express provisions of this Chapter as may appear to it to be necessary or expedient for the removal of the doubt or difficulty, and the order of the Government, in such cases, shall be final.]
Section 23 Powers of entry.
The Authority may authorise any person to enter into or upon any land or building with or without assistants or workmen for the purpose of––
(a) making any enquiry, inspection, measurement or survey or taking levels of such land or building ;
(b) examining work under construction and ascertaining the course of sewers and drains ;
(c) digging or boring into the sub-soil ;
(d) setting out boundaries and intended lines of work ;
(e) making such levels, boundaries and lines by placing marks and cutting trenches ;
(f) ascertaining whether any land is being or has been developed in contravention of the master plan or zonal plan or without the permission referred to in section 13 or in contravention of any condition subject to which such permission has been granted ; or
(g) doing any other thing necessary for the efficient administration of this Act :
Provided that––
(i) no such entry shall be made except between the hours of sunrise and sunset without giving reasonable notice to the occupier, or if there be no occupier, to the owner of land or building ;
(ii) sufficient opportunity shall in every instance be given to enable women (if any) to withdraw from such land or building ;
(iii) due regard shall always be had, so far as may be compatible with the exigencies of the purpose for which the entry is made to the social and religious usages of the occupants of the land or building entered.
(a) making any enquiry, inspection, measurement or survey or taking levels of such land or building ;
(b) examining work under construction and ascertaining the course of sewers and drains ;
(c) digging or boring into the sub-soil ;
(d) setting out boundaries and intended lines of work ;
(e) making such levels, boundaries and lines by placing marks and cutting trenches ;
(f) ascertaining whether any land is being or has been developed in contravention of the master plan or zonal plan or without the permission referred to in section 13 or in contravention of any condition subject to which such permission has been granted ; or
(g) doing any other thing necessary for the efficient administration of this Act :
Provided that––
(i) no such entry shall be made except between the hours of sunrise and sunset without giving reasonable notice to the occupier, or if there be no occupier, to the owner of land or building ;
(ii) sufficient opportunity shall in every instance be given to enable women (if any) to withdraw from such land or building ;
(iii) due regard shall always be had, so far as may be compatible with the exigencies of the purpose for which the entry is made to the social and religious usages of the occupants of the land or building entered.
Section 24 Penalties.
(1) Any person who whether at his own instance or at the instance of any other person or anybody (including a Department of Government or of a local body) undertakes or carries out development in contravention of the zonal plan or without the permission, referred to in section 13 or in contravention of any condition subject to which such permission, has been granted, shall be punishable with fine which may extend to 1[Rs. 50,000/-] and in the case of continuing offence, with further fine which may extend to 2[Rs. 2000/-] for everyday during which such offence continues after conviction for the first commission of the offence.
(2) Any person who uses any land or building in contravention of the provision of section 15 or in contravention of any terms and conditions prescribed by regulations under the proviso to that section shall be punishable with fine which may extend to 3[Rs. 30,000/-] and in the case of a continuing offence, with further fine which may extend to 4[Rs. 1,500/-] for everyday during which such offence continues after conviction for first commission of the offence.
(3) Any person who obstructs the entry of a person authorised under section 23 to enter into or upon any land or building or molests such person after such entry shall be punishable with imprisonment for a term which may extend to six months, or with fine which may extend to one thousand rupees, or with both.
(2) Any person who uses any land or building in contravention of the provision of section 15 or in contravention of any terms and conditions prescribed by regulations under the proviso to that section shall be punishable with fine which may extend to 3[Rs. 30,000/-] and in the case of a continuing offence, with further fine which may extend to 4[Rs. 1,500/-] for everyday during which such offence continues after conviction for first commission of the offence.
(3) Any person who obstructs the entry of a person authorised under section 23 to enter into or upon any land or building or molests such person after such entry shall be punishable with imprisonment for a term which may extend to six months, or with fine which may extend to one thousand rupees, or with both.
1. Substituted for “Rs. 5000/-” by S.O. 3808 (E) dated 26.10.2020.
2. Substituted for “Rs. 200/-” ibid.
3. Substituted for “Rs. 3000/-” by S.O. 3808 (E) dated 26.10.2020.
4. Substituted for “Rs. 150/-” ibid.
2. Substituted for “Rs. 200/-” ibid.
3. Substituted for “Rs. 3000/-” by S.O. 3808 (E) dated 26.10.2020.
4. Substituted for “Rs. 150/-” ibid.
Section 25 Order of demolition of building.
(1) Where any development has been commenced or is being carried on or has been completed in contravention of a zonal plan or without the permission, referred to in section 13, or in contravention of any conditions subject to which such permission has been granted, any officer of the Authority empowered by it in this behalf may, in addition to any prosecution that may be instituted under this Act, make an order directing that such development shall be removed by demolition, filling or otherwise by the owner thereof or by the person at whose instance the development has been commenced or is being carried out or has been completed, within such period (not being less than five days, and more than fifteen days from the date on which a copy of the order of removal, with a brief statement of the reasons therefor has been delivered to the owner or that person) as may be specified in the order and on his failure to comply with the order, the officer of the Authority may remove or cause to be removed the development and the expenses of such removal shall be recovered from the owner or the person at whose instance the development was commenced or was being carried out or was completed, as arrears of land revenue :
Provided that no such order shall be made unless the owner or the person concerned has been given a reasonable opportunity to show cause why the order should not be made.
(2) Any person aggrieved by an order under sub-section (1) may appeal to the Government against that order within thirty days from the date thereof, and the Government may after hearing the parties to the appeal, either allow or dismiss the appeal or may reverse or vary any part of the order.
(3) The decision of the Government on the appeal and subject only to the such decision, the order under sub-section (1) shall be final and shall not be questioned in any Court.
Provided that no such order shall be made unless the owner or the person concerned has been given a reasonable opportunity to show cause why the order should not be made.
(2) Any person aggrieved by an order under sub-section (1) may appeal to the Government against that order within thirty days from the date thereof, and the Government may after hearing the parties to the appeal, either allow or dismiss the appeal or may reverse or vary any part of the order.
(3) The decision of the Government on the appeal and subject only to the such decision, the order under sub-section (1) shall be final and shall not be questioned in any Court.
Section 26 Power to stop development.
(1) Where any development in any area has been commenced in contravention of a zonal plan, or without the permission, referred to in section 13 or in contravention of any conditions subject to which such permission has been granted, the Authority or any officer of the Authority empowered by it in this behalf may, in addition to any prosecution that may be instituted under this Act and without prejudice to the provisions of section 25, make an order requiring the development to be discontinued on and from the date of the service of the order, and such order shall be complied with accordingly.
(2) Where such development is not discontinued in pursuance of the order under sub-section (1), the Authority or the officer of the Authority or the competent authority, as the case may be, may require any police officer to remove the person by whom the development has been commenced and all his assistants and workmen from the place of development, within such time as may be specified in the requisition, and such police officer shall comply with the requisition accordingly.
(3) After the requisition under sub-section (2) has been complied with, the Authority or the officer of the Authority, as the case may be, may depute by a written order a police officer or an officer or employee of the Authority to watch the place in order to ensure that the development is not continued.
(4) Any person failing to comply with an order under sub-section (1) shall be punishable with fine which may extend to 1[two thousand rupees] for everyday during which the non-compliance continues after the service of the order.
(5) No compensation shall be claimable by any person for any damage which he may sustain in consequence of the removal of any development under section 25 or the discontinuance of the development under this section.
(2) Where such development is not discontinued in pursuance of the order under sub-section (1), the Authority or the officer of the Authority or the competent authority, as the case may be, may require any police officer to remove the person by whom the development has been commenced and all his assistants and workmen from the place of development, within such time as may be specified in the requisition, and such police officer shall comply with the requisition accordingly.
(3) After the requisition under sub-section (2) has been complied with, the Authority or the officer of the Authority, as the case may be, may depute by a written order a police officer or an officer or employee of the Authority to watch the place in order to ensure that the development is not continued.
(4) Any person failing to comply with an order under sub-section (1) shall be punishable with fine which may extend to 1[two thousand rupees] for everyday during which the non-compliance continues after the service of the order.
(5) No compensation shall be claimable by any person for any damage which he may sustain in consequence of the removal of any development under section 25 or the discontinuance of the development under this section.
1. Substituted for “two hundred rupees” by S.O. 3808 (E) dated 26.10.2020.
Section 27 Offences by companies.
(1) If the person committing any offence under this Act is a company, every person, who at the time the offence was committed, was incharge of, and was responsible to, the company for the conduct of the business of the company as well as the company shall be deemed to be guilty of the offence and shall be liable to be proceeded against and punished accordingly : Provided that nothing contained in this sub-section shall render any such person liable to any punishment provided in this Act if he proves that the offence was committed without his knowledge or that he exercised all due diligence to prevent the commission of such offence.
(2) Notwithstanding anything contained in sub-section (1), where an offence under this Act has been committed by a company and it is proved that the offence has been committed with the consent or connivance of, or is attributable to any neglect on the part of, any director, manager, secretary, or other officer of the company, such director, manager, secretary, or other officer shall also be deemed to be guilty of that offence and shall be liable to be proceeded against and punished accordingly.
Explanation.––For the purposes of this section “Company” means a body corporate and includes a firm or other association of individuals.
(2) Notwithstanding anything contained in sub-section (1), where an offence under this Act has been committed by a company and it is proved that the offence has been committed with the consent or connivance of, or is attributable to any neglect on the part of, any director, manager, secretary, or other officer of the company, such director, manager, secretary, or other officer shall also be deemed to be guilty of that offence and shall be liable to be proceeded against and punished accordingly.
Explanation.––For the purposes of this section “Company” means a body corporate and includes a firm or other association of individuals.
Section 28 Fines when realised to be paid to authority.
All fines realised in connection with prosecutions under this Act shall be paid to the Authority.
Section 29 Composition of Offences.
(1) Any offence made punishable by or under this Act, may, either before or after the institution of proceedings, be compounded by the Authority or any person authorised by the Authority by general or special order in this behalf.
(2) Where an offence has been compounded the offender, if in custody, shall be discharged and no further proceeding shall be taken against him in respect of the offence compounded.
(2) Where an offence has been compounded the offender, if in custody, shall be discharged and no further proceeding shall be taken against him in respect of the offence compounded.
Section 30 Default powers of Authority.
(1) If the Authority after holding a local enquiry or upon report from any of its officers or other information in its possession, is satisfied that any amenity in relation to any land or building in a zone has not been provided in relation to any land or building which in the opinion of the Authority is to be provided, it may, after affording a reasonable opportunity to show cause, serve upon the person providing or responsible for providing amenity a notice requiring him to provide the amenity or carry out the development within such time as may be specified in the notice.
(2) If any amenity is not provided or any such development is not carried out within the time specified in the notice, then the Authority may itself provide the amenity or carry out the development or have it provided or carried out through such agency as it deems fit :
Provided that before taking any action under this sub-section, the Authority shall afford reasonable opportunity to the person providing or responsible for providing the amenity to show cause as to why such action should not be taken.
(3) All expenses incurred by the Authority or the agency employed by it in providing the amenity or carrying out the development together with interest at such rate as the Government by order fix from the date when a demand for the expenses is made until payment may be recovered by the Authority from the person providing or responsible for providing the amenity, as arrears of land revenue.
(2) If any amenity is not provided or any such development is not carried out within the time specified in the notice, then the Authority may itself provide the amenity or carry out the development or have it provided or carried out through such agency as it deems fit :
Provided that before taking any action under this sub-section, the Authority shall afford reasonable opportunity to the person providing or responsible for providing the amenity to show cause as to why such action should not be taken.
(3) All expenses incurred by the Authority or the agency employed by it in providing the amenity or carrying out the development together with interest at such rate as the Government by order fix from the date when a demand for the expenses is made until payment may be recovered by the Authority from the person providing or responsible for providing the amenity, as arrears of land revenue.
Section 31 Powers of Authority to require local authority to assume responsibility for amenities in certain cases.
Where any area has been developed by the Authority, the Authority may require the local authority or a department of the Government within whose local limits the area so developed is situated, to assume responsibility for the maintenance of the amenities which have been provided in the area by the Authority and for the provision of the amenities which have not been provided by the Authority but which in its opinion should be provided in the area, 1[x x x x].
1. Certain words omitted by S.O. 3808 (E) dated 26.10.2020.
Section 32 Power of levy betterment charges.
(1) Where in the opinion of the Authority, as a consequence of any development having been in any zone, the value of any property in that zone or executed by the Authority in any area other than the zone, which has been benefited by the development, has increased or will increase, the Authority shall be entitled to levy upon the owner of the property or any person having an interest therein a betterment charge in respect of the increase in value of the property resulting from the execution of the development : Provided that no betterment charge shall be levied in respect of lands owned by Government or any local authority.
(2) Such betterment charges shall be an amount––
(i) in respect of any property situate in a zone equal to one-third of the amount, and
(ii) in respect of property situate in any other area not exceeding one-third of the amount,
by which the value of the property on the completion of the execution of the development estimated as if the property were clear of buildings, exceeds the value of the property prior to such execution estimated in like manner :
Provided that in levying betterment charges on any property under clause (ii), the Authority shall have regard to the extent and nature of benefit accruing to the property from the development and such other factors as may be prescribed by rules made in this behalf.
(2) Such betterment charges shall be an amount––
(i) in respect of any property situate in a zone equal to one-third of the amount, and
(ii) in respect of property situate in any other area not exceeding one-third of the amount,
by which the value of the property on the completion of the execution of the development estimated as if the property were clear of buildings, exceeds the value of the property prior to such execution estimated in like manner :
Provided that in levying betterment charges on any property under clause (ii), the Authority shall have regard to the extent and nature of benefit accruing to the property from the development and such other factors as may be prescribed by rules made in this behalf.
Section 33 Assessment of betterment charges by Authority.
(1) When it appears to the Authority that any particular development plan is sufficiently advanced to enable the amount of the betterment charges to be determined, the Authority may, by an order made in this behalf, declare that for the purpose of determining the betterment charges the execution of the plan shall be deemed to have been completed and shall thereupon give notice in writing to the owner of the property or any person having an interest therein that the Authority proposes to assess the amount of the betterment charge in respect of the property under section 32.
(2) The Authority shall then assess the amount of betterment charges payable by the person concerned after giving such person an opportunity to be heard and such person shall, within three months from the date of receipt of the notice in writing of such assessment from the Authority, inform the Authority by a declaration in writing that he accepts the assessment or dissents from it.
(3) When the assessment proposed by the Authority is accepted by the person concerned within the period specified in sub-section (2), such assessment shall be final.
(4) If the person concerned dissents from the assessment or fails to give the Authority the information required by sub-section (2) within the period specified therein, the matter shall be determined by an arbitrator in the manner provided in section 34.
(2) The Authority shall then assess the amount of betterment charges payable by the person concerned after giving such person an opportunity to be heard and such person shall, within three months from the date of receipt of the notice in writing of such assessment from the Authority, inform the Authority by a declaration in writing that he accepts the assessment or dissents from it.
(3) When the assessment proposed by the Authority is accepted by the person concerned within the period specified in sub-section (2), such assessment shall be final.
(4) If the person concerned dissents from the assessment or fails to give the Authority the information required by sub-section (2) within the period specified therein, the matter shall be determined by an arbitrator in the manner provided in section 34.