THE JAMMU AND KASHMIR WATER RESOURCES (REGULATION AND MANAGEMENT) ACT, 2010

Administered Ministry: NO MINISTRY / PHE(I&FC)

Showing 21 to 40 of 202 results
Section
Section 21 Power to enter premises.
(1) The Assistant Executive Engineer or any Gazetted officer, authorised in this behalf by the Executive Engineer concerned, may between 9.A.M to 5.P.M enter into any premises for the purpose of inspecting any water installation in any building, site or premises.

(2) If such officer is, at any such time, refused admittance into such building, site or premises for the purpose aforesaid or is prevented from making such inspection, the Executive Engineer may, after giving the owner or occupier of such building, site or premises an opportunity of being heard, cut off the supply of water to such building, site or premises :

Provided that if any such place is an apartment in the actual occupancy of a woman who, according to custom, does not appear in public, such officer shall, before entering such apartment, give notice to such woman that she is at liberty to withdraw and shall afford her every reasonable facility for withdrawing, and may then enter the apartment.

(3) The power conferred by this section includes the power to break open the door where the Executive Engineer or such Gazetted Officer has reason to believe that the water is being misused or used without proper permission :

Provided that the power to break open the door shall be exercised only after the owner or any other person in occupation of the premises, if he is present therein, refuses to open the door on being called to do so.

(4) The provisions of the Code of Criminal Procedure, Samvat 1989 shall, so far as may be, apply to any search or seizure under this section as they apply to any search or seizure made under the authority of a warrant issued under the said Code.
Section 22 Cutting of water supply.
(1) Notwithstanding anything contained in the Act, the Executive Engineer may cut off the supply of water to any premises or may turn off such supply on any one of the following grounds, namely :––

(a) if, after the receipt of a written notice from the Assistant Executive Engineer concerned requiring him to refrain from so doing, the owner or occupier of the premises continues to use the water or to permit the same to be used in contravention of the Act or the rules and regulations framed thereunder ;

(b) if any pipe, tap, work or fitting connected with the supply of water to the premises is found, on inspection in this behalf, to be damaged or out of repair to such an extent so as to cause waste or contamination of water and immediate prevention is necessary ;

(c) if there is any water-pipe situated within the premises to which no tap or other efficient means of turning off the water is attached ;

(d) if, by reason of a leakage in the pipe or fitting, damage is caused to the public street and immediate prevention is necessary ; or

(e) if the owner of the premises refuses of fails to pay, for a period of one month after he has been served with a notice of demand, water charges on account of water consumed in the premises.

(2) When the water has been cut off or turned off under clause (e) of subsection (1), the Assistant Executive Engineer concerned may, on such terms and conditions as may be prescribed, recommend restoration of the water supply on payment of water usage charges.
Section 23 Appeals.
(1) Subject to the provision of sub-section (2), an appeal shall lie from every order of the Executive Engineer or the prescribed authority made under sub-section (3) of section 8, or from every order of the Executive Engineer made under sections 21 and 22,––

(i) to the Authority, if such order is made by the prescribed authority ; and

(ii) to the Superintending Engineer concerned, if such order is made by the Executive Engineer.

(2) Every such appeal shall be preferred within ninety days from the date of order :

Provided that the Authority or the Superintending Engineer, as the case may be, may entertain an appeal after the expiry of the said period of ninety days if it or he is satisfied that the appellant was prevented by sufficient cause from filing it in time.

(3) On receipt of any such appeal, the Authority or the Superintending Engineer, as the case may be, shall, after giving the appellant a reasonable opportunity of being heard and after making such enquiry as it or he deems proper, dispose of the appeal within a period of four months from the date of its institution.

(4) The decision of the Authority or the Superintending Engineer, as the case may be, on such appeal shall be final.
Section 24 Usage of water for irrigation.
(1) Whenever it appears expedient to the Government that water received from any water source including any natural collection of still or ground water whether by percolation, regeneration, release, or otherwise should be applied or used for the purpose of any existing or projected irrigation work or for the regulation, supply or storage of water, the Government may, by notification, declare that the said water shall be so applied or used after a day to be specified in the said notification, not being earlier than three months from the date thereof.

(2) After issuance of a notification under sub-section (1), the Assistant Executive Engineer shall cause a public notice to be given at convenient places, indicating the intention of the Government to apply or use water for the purposes indicated in the notification.

(3) The application or use of the said water or the application or use of water of any irrigation source under the management or control of the Government shall be regulated according to the provisions of the Act.

(4) Where the Government is of the opinion that in the interests of proper irrigation from any irrigation work constructed or proposed to be constructed it is necessary to control the construction of wells for any purpose other than exclusive domestic use, either on personal or community basis, in any area, the Government may, by notification, specify such area and on issue of such notification, no person shall within such area construct or cause to be constructed any such well except with the previous sanction of the Government or any officer authorised by the Government in this behalf and subject to such conditions as the Government or such officer may impose.

(5) Where the Government is of the opinion that in the interest of proper irrigation, any land under existing or proposed irrigation work is to be transferred to another work or proposed work or completely excluded from any existing work, the Government may, by notification, specify such land and such works to take effect from a date specified in the notification not being earlier than one month from the date thereof.
Section 25 Powers of entry on land etc.
At any time after the day specified in the notification under sub-section (1) of section 24, an Assistant Executive Engineer may enter on premises or any land or remove any obstruction or close any channel or do any other thing necessary for such application or use of the said water and for the said purpose, he may seek the help of police or any other authority as he thinks fit.
Section 26 Power to enter and survey etc.
Whenever it shall be necessary to make an inspection, enquiry or examination in connection with a projected irrigation work or its construction or with the maintenance of an existing irrigation work or with the application or use of the water of any irrigation work for the purpose of regulation, supply or storage of water, the Assistant Executive Engineer concerned may––

(a) enter upon such land, premises or structure or anything attached to the said land, premises or structure as he may think necessary for the purpose ;

(b) undertake inspection, surveys or take levels thereon ;

(c) dig and bore into the sub-soil ;

(d) cause any standing crop, fence or jungle to be cleared or removed for conducting such inspection, survey or investigation ;

(e) exercise all powers and do all things necessary for such inspection, survey or investigation in respect of such land as he might exercise and do if the Government had issued a notification under section 4 of the State Land Acquisition Act, Samvat 1990 to the effect that land in that locality is likely to be needed for public purpose ; and

(f) set up and maintain gauge discharge and silt measurement stations and do all other things necessary for purposes of such inspection, inquiry and examination.
Section 27 Power to enter upon land, building etc, for inspection.
The Assistant Executive Engineer concerned, may for the purpose of inspecting or regulating use of the water supplied, or for measuring the land irrigated thereby, enter upon any land, water course or field channel on account of which any water rate is chargeable and for doing all things necessary for the proper regulation and management of the irrigation work from which such water is supplied.
Section 28 Power to enter for repairs and to prevent accidents.
(1) In case of occurrence, or apprehension, of an accident to an irrigation work or flood control work, the Assistant Executive Engineer concerned or any other person authorised by him in this behalf, may enter upon or into any immovable property in the neighbourhood of such irrigation or flood control work as may be necessary for repairing any damage done or for preventing such accident and remove, carry or utilise trees and other material and take such other steps, and execute any work as may be necessary for such purpose.

(2) If any person suffers any loss or damage as a result of removal or clearance of standing crops or felling and carrying of trees, he shall be paid compensation for such loss or damage in accordance with the provisions of Chapter V of the Act.
Section 29 Notice to an occupier of building.
(1) Where the Assistant Executive Engineer intends to enter any building, premises or any land appurtenant thereto under the provisions of sections 25 to 28, he shall give to the occupier of such building or premises a reasonable prior notice as the urgency of the case may allow.

(2) The power conferred by sections 25 to 28 includes the power to break open the door of any premises for purposes of removing any obstruction or for undertaking inspection, survey, digging, clearing any crop, fence or jungle or doing repairs or preventing accidents or doing any other thing necessary for construction, maintenance or regulating the supply of an irrigation work :

Provided that the power to break open the door shall be exercised only after the owner or any other person in occupation of the premises, if he is present therein, refuses to open the door on being called to do so:

Provided further that if any such place is an apartment in the actual occupancy of a woman who, according to custom, does not appear in public, such officer shall, before entering such apartment, give notice to such woman that she is at liberty to withdraw and shall afford her every reasonable facility for withdrawing, and may then enter the apartment.

(3) The provisions of the Code of Criminal Procedure, Samvat 1989 shall, so far as may be, apply to any search or seizure under this section as they apply to any search or seizure made under the authority of a warrant issued under the said Code.
Section 30 Canal crossings.
(1) The Government shall provide and maintain suitable means of canal crossings at such places as the Government thinks necessary for the reasonable convenience of the inhabitants of the adjacent land.

(2) No suit or any proceeding shall lie against the Government for enforcing the construction of a canal crossing, or for enforcing the alternation of a crossing or for compensation for damage arising from the absence or inadequacy of any crossing, or for modifying or setting aside any scheme framed or order passed under this section.

Explanation:––Suitable means of canal crossing include means the passage of traffic and of water.
Section 31 Acquisition of land for irrigation works.
If the Government is satisfied that any land is required for the construction of an irrigation work excluding water courses, field channels and field drains, or for the maintenance, improvement or extension of an existing irrigation work, the Government may acquire the land in accordance with the provisions of the State Land Acquisition Act, Samvat 1990.
Section 32 Preparation of draft scheme.
(1) The Executive Engineer concerned may, on his own motion or on an application made by owners or occupiers of any land or field, prepare or cause to be prepared a draft scheme to provide for all or any of the matters, namely :––

(a) construction, alteration, extension and re-alignment of any water channel, or any existing water channel constructed or maintained by any owner or occupier ;

(b) re-allotment of areas served by one water course to another ;

(c) lining of any water channel ;

(d) occupation of land for the deposit of soil gathered from clearance of any water channel ;

(e) any other matter which is necessary for proper maintenance and distribution of supply of water from a water course.

(2) Every scheme prepared under sub-section (1) shall amongst other matters, set out the estimated cost thereof, the re-alignment of any water channel or existing water channel, as the case may be, the site of the outlet, the particulars of the owners or occupiers or the persons to be benefited or the persons who may be affected thereby, and a sketch plan of the area proposed to be covered by the scheme.
Section 33 Publication of the Scheme
(1) Every scheme shall, as soon as may be after its preparation, be published in such form and manner as may be specified for inviting objections and suggestions with respect thereof within thirty days from the date of its publication.

(2) After considering of such objections and suggestions if any, the Executive Engineer shall approve the scheme either as it was originally published or in such modified form as he may consider fit and publish the same.

(3) The Superintendent Engineer may, on his own motion at any time or on an application made, within a period of thirty days from the date of publication of a scheme, by any person aggrieved by such scheme, revise the scheme approved under sub-section (2) :

Provided that such revision shall not be made without affording the person affected an opportunity of being heard.

(4) Any person aggrieved by an order of Executive Engineer under subsection (2), or Superintendent Engineer under sub-section (3), may prefer an appeal, within period of thirty days of passing of such order, to the prescribed authority whose decision thereon shall be final.
Section 34 Acquisition of land for water channels and field channels.
After a scheme has been approved by the Executive Engineer under sub-section (2), or revised by the Superintending Engineer under sub-section (3), or where an appeal has been preferred before the prescribed authority under sub-section (4), after it has been disposed of, the Executive Engineer shall, acquire the land by agreement with the owner thereof, or initiate the process of acquiring the land by the Government in accordance with the provisions of the State Land Acquisition Act, Samvat 1990.
Section 35 Implementation of Scheme.
(1) The Executive Engineer shall, after taking possession of the land acquired under section 34, take steps for implementation of the scheme.

(2) Any scheme constructed under sub-section (1) shall be the property of the Government.

(3) Unless ordered by the Government to the contrary, any extension, alteration or re-alignment of water channels at the instance of any owner or occupier shall be done at the cost of such owner or occupier.
Section 36 Maintenance of water channels.
On execution of the scheme, the Executive Engineer shall, by order in writing, direct the owners, occupiers or beneficiaries to take over and maintain the water channel and on failure of any owner or occupier or beneficiary to comply with this direction, he shall make arrangements for maintenance of the water channel at the cost of such owners or occupiers or beneficiaries in proportion to the culturable commanded area under the scheme held by them.
Section 37 Persons using water course to construct works.
(1) The Assistant Executive Engineer may issue an order to the persons using any field channel to construct suitable bridges, culverts or other works as approved by the Assistant Executive Engineer for the passage of the water of such field channel across any public road, canal or drainage channel in use before the said field channel was made or to repair any such works.

(2) The order issued under sub-section (1) shall specify a reasonable period within which such construction or repairs shall be completed.

(3) If, after the receipt of such order, the person to whom it is addressed does not, within the said period, construct or repair such work to the satisfaction of the Assistant Executive Engineer, he may with the approval of Executive Engineer, himself construct or repair the same, and demand the cost of such construction or repairs from the defaulting person responsible for such construction or repair.
Section 38 Protection of water channels against demolition etc.
(1) if a person demolishes, alters, enlarges, obstructs or encroaches upon a water channel or field channel or causes any damage thereto, any person affected thereby may apply to the Assistant Executive Engineer for directing the restoration of the water channel or field channel to its original condition.

(2) The Assistant Executive Engineer may, on his own motion or on the information given by village Patwari, Lambardar or any other person or on receiving an application under sub-section (1), after making such enquiry as he may deem fit, require, by a notice in writing served on the persons found to be responsible for so demolishing, altering, enlarging, obstructing, encroaching or causing damage, to restore at his own cost the water course or field channel to its original condition within such period as may be specified in the notice.

(3) If such person fails to restore, to the satisfaction of the Assistant Executive Engineer, the water channel or field channel to its original condition within the period specified in the notice served on him under sub-section (2), the Assistant Executive Engineer may cause the water channel or field channel to be restored to its original condition and recover the cost incurred on such restoration from the defaulting person.

(4) Any person aggrieved by the order of the Assistant Executive Engineer may prefer an appeal, within thirty days of the passing of such order, to the Executive Engineer, whose decision on such appeal shall be final.
Section 39 Adjustment of claims between persons jointly using water channel.
(1) If any person, jointly responsible with others for the maintenance of a water channel or field channel, or jointly making use of a water channel with others, neglects or refuses to pay his share of the maintenance or to execute his share of any work necessary for such maintenance, the Assistant Executive Engineer shall, on receiving an application in writing from any person affected by such neglect or refusal, investigate the case and make such order thereon as he deems fit.

(2) The order passed under sub-section (1) shall be appealable to the Executive Engineer, whose decision thereon shall be final.
Section 40 Supply of water through intervening water channel.
(1) Whenever application is made to a Assistant Executive Engineer for supply of water from an irrigation work, and it appears to him expedient that such supply should be given and that it should be conveyed through a field channel, he shall give notice to the persons responsible for the maintenance of such field channel to show cause on a day not less than seven days from the date of such notice as to why the said supply should not be so conveyed, and after making enquiry on such day, the Assistant Executive Engineer shall determine whether and on what conditions the said supply shall be conveyed through such field channel :

Provided that such application is made for lands already included in the irrigation works.

(2) Any person, aggrieved by the determination of the Assistant Executive Engineer, may prefer an appeal to the Executive Engineer within a period of thirty days of such determination.

(3) When the Assistant Executive Engineer determines that supply of water of an irrigation work shall be conveyed through a field channel, his decision shall, when confirmed or modified by the Executive Engineer on appeal, be binding on the applicant and also on the persons responsible for the maintenance of the said field channel.

(4) Such applicant shall not be entitled to use such field channel until he has paid the expenses of alteration of such field channel and also such share of the first cost of such field channel as the Assistant Executive Engineer or the Executive Engineer, as the case may be, may determine.

(5) Such applicant shall also be liable for his share of the cost of maintenance of such field channel so long as he uses it.