Section 101 Revocation of licence.
(1) If the licensing authority, after making an enquiry, is satisfied that public interest so requires, it may revoke a licence in any of the following cases, namely :––

(a) where the licensee, in the opinion of the licensing authority, makes wilful or prolonged default in doing anything required of him by or under the Act or the rules or regulations made thereunder ;

(b) where the licensee violates any of the terms and conditions of his licence, the violation of which is expressly declared by such licence to render it liable to revocation ;

(c) where the licensee fails, within the period fixed in this behalf by the licence, or any longer period which the licensing authority may have granted therefor, to––

(i) show to the satisfaction of the licensing authority that the licensee is in a position to discharge fully and efficiently the duties and obligations imposed on him by his licence ; or

(ii) make the deposit or furnish the security or pay the fees or other charges required by his licence ;

(d) where in the opinion of the Authority or the Government, as the case may be, the financial position of the licensee is such that he is unable to discharge fully and efficiently the duties and obligations imposed on him by his licence.

(2) Where in its opinion the public interest so requires, the licensing authority may, on application, or with the consent, of the licensee revoke his licence as to the whole or part of his area of operation on such terms and conditions as it thinks fit.

(3) No licence shall be revoked under sub-section (1) unless the licensing authority has given to the licensee not less than three months notice in writing specifying the grounds on which it is proposed to revoke the licence, and has considered any cause shown by the licensee within the period of that notice, against the proposed revocation.
Section 102 Duties, obligations and respon-sibilities of the licensee.
(1) It shall be the duty of the licensee to develop and maintain an efficient coordinated system for the economical and optimum utilization of water and distribution of the same in accordance with the provisions of the Act.

(2) The licensee shall be liable to pay water usage charges (tariff) for the water utilized as per the provisions of the Act.

(3) Where any user has constructed an irrigation scheme, drinking water supply scheme, dam (for purpose of generation of electricity), or any other hydraulic structure or installed any unit for usage of water prior to the commencement of the Act, such user shall, within a period of six months from the date of commencement of the Act, apply for a licence under the Act and the licensing authority shall pass an order with regard to grant of license within a period of six months from the date of receipt of application in accordance with the provisions of the Act.

(4) If the user as mentioned in sub-section (3) fails to apply or obtain a licence within the time stipulated therein, the prescribed authority shall forthwith stop the supply of water to him until he obtains a licence as per the provisions of the Act.

(5) Every licensee shall be under an obligation to ensure the safety of the life and property of inhabitants of the area under the operation of the scheme, and of water sources and hydraulic works and protection thereof against any damage or danger caused or likely to be caused by the uncontrolled release of water or hazardous waste caused by the collapse or failure of any unit, dam, barrage or hydraulic work.

(6) Every licensee shall be bound to allow the licensing authority or any other officer authorised by licensing authority to have access at any time to the design, construction, alteration, repair, maintenance and operation of the licensed unit for its satisfaction.

(7) Every licensee shall provide efficient services to the consumers as required under the terms and conditions of the licence.

(8) Every licensee shall be bound to follow and observe such safety measures as may be specified by the Authority under section 105.
Section 103 Grievance redressal mechanism.
(1) Every licensee shall establish a mechanism for redressal of the grievances of the people or consumers in accordance with such guidelines as may be specified by the Authority.

(2) Any person who is aggrieved by non-redressal of his grievances under sub-section (1), may make a representation for redressal of his grievances to the Authority.

(3) The Authority shall settle the grievances of such person within such time and in such manner as it may think fit.
Section 104 Directions to the Licensee.
The Government may, in extraordinary circumstances, require a licensee to operate and maintain his unit in accordance with such directions as may be issued by the it from time to time.

Explanation:––For purposes of this section, the extraordinary circumstances mean the circumstances arising out of the threat to the security of the state, public order or a natural calamity.
Section 105 Control and safety provisions.
(1) The Authority may, in consultation with the Government, specify suitable measures to be adopted by a licensee which are necessary for––

(a) protecting the public, including the persons engaged in the usage of water for the purposes of generation of power, running of water in irrigation and water supply units, hydraulic works, exploration of ground water and construction activities on such units for purposes of the usage of water ;

(b) eliminating or reducing the risk of personal injury to any person or damage to property of any person during the currency of licence ;

(c) ensuring the safety of the life and property of the inhabitants of the area under the operation of the scheme, water source, hydraulic work and protection thereof against any damage or danger caused or likely to be caused by the uncontrolled release of water or hazardous waste caused by the collapse or failure of any unit, dam, barrage or hydraulic work.

(2) For purposes of clause (c) of sub-section (1), the licensing authority or any officer or authority authorised by it shall exercise all powers and perform all functions and duties that are necessary for ensuring that the licensee complies with the safety measure specified by the Authority under sub-section (1) or those specified in the terms of the licence.

(3) The licensing authority may from time to time require re-examination and modification of designs, plans and specification of initial construction or any subsequent alteration, repairs, maintenance and operation licensed unit in consultation with an expert having experience in the design and construction of such units or works.

(4) The licensing authority may, by notice in writing given to the licensee, require him to––

(a) cause periodic inspection carried out by an expert, to the satisfaction of the licensing authority and in accordance with the procedure and at such intervals, as the licensing authority may specify, of the water usage unit ;

(b) cause to be carried out by an expert having experience in the design and construction of such units or works a review of the design, construction and operating procedures of the water usage unit and furnish a report of the same to the licensing authority ;

(c) carry out such repairs or take such measures as specified in the notice to ensure the safety of the unit and the protection of life and property that is likely to be endangered by the uncontrolled release of water or hazardous waste likely to be caused by the collapse or failure of the unit.

(5) The licensing authority shall forward a copy of notice given under sub-section (4) to the Authority for information and record.

(6) The licensee shall pay such fee and such other charges as the Authority may fix in this behalf, to the licensing authority for undertaking the following activities :––

(a) periodical inspection of the unit by the licensing authority or any other officer or expert empowered in this behalf ;

(b) any other activity performed or caused to be performed by the licensing authority under this section in relation to the unit of the licensee.
Section 106 Location of Dams to be away from populated area.
While issuing a licence for establishment of a unit for generation of electricity, the licensing authority shall ensure that––

(a) the site of the dam of such unit is reasonably away from the thickly populated area ;

(b) the licensee executes all anti-erosion works, bunds or other mechanisms in case the outgoing water from the turbine after generating electricity flowing down the dam site is likely to cause erosion of land of, or inundation or submergence of, any area ;

(c) the licensee installs and operates automatic warning system with hooters or sirens so as to warn the people regarding operation of ejection of silt from the dam ; and

(d) the licensee undertakes to deploy regular guards for giving advance warning to the people living in the adjoining villages so that they evacuate the area during emergent situations.
Section 107 Power of licensing authority under this Chapter.
For the purpose of this Chapter, the licensing authority shall have the following powers in relation to a unit or the licensee––

(a) to measure and record the water resources of both surface and underground used by a licensee ;

(b) to permit use water from any watercourse, or any other source for establishment of a unit by a licensee ;

(c) to allow diversion, interception and storage of water coming from any water source ;

(d) to allow usage of surface water or ground water ;

(e) to enter upon any land or premises for the purposes of––

(i) making or carrying out inspection, tests, investigations, surveys, experiments, boring or drilling operations, explorations, etc. ;

(ii) satisfying itself with design, construction, operations and maintenance or alterations of licensed units ; and

(iii) taking all steps and doing all acts and things connected with, or incidental to, the exercise or performance of the powers, functions and duties conferred by or under the Act ;

(f) to satisfy itself with blasting operations ; and

(g) to take all steps and do all acts and things as are necessary for or in connection with the performance of the operations specified in this section.
Section 108 Liability for failure or collapse of water usage unit.
(1) The licensee shall be responsible for any injury, loss or damage caused by or resulting from the total or partial failure or collapse of, or the escape of hazardous waste from the unit and shall be liable to make good such loss, injury or damage and bear all expenses to be incurred on re-construction or restoration of the injured, lost or damaged infrastructure apart from any compensation that may be payable to the sufferers under any law for the time being in force.

(2) The approval of the design, construction, operation and maintenance of the unit by the Authority or the Government, as the case may be, shall not absolve the licensee from the liability under sub-section (1).
Section 109 Special Works.
(1) For the establishment of a unit for usage of water, the licensing authority may, if it considers it necessary or on the request of a licensee, permit the licensee to undertake certain special works which may include the following :––

(a) diversion of a water course ;

(b) reclamation of water-course, lake or swamp land or part thereof ;

(c) works associated with a mining development or mining operations ; or

(d) any other work connected with or necessary for installation of the unit by a licensee.

(2) A licensee may apply to the licensing authority accompanied by such fee as may be prescribed, for obtaining permission for undertaking any such special work justifying the necessity and relation of such work with respect to the approved unit with detailed description in regard to––

(a) the lawful ownership and possession of the land proposed to be used or operated ;

(b) land to be acquired for the use or operation ;

(c) easements to be acquired, in connection with the proposed works ;

(d) the persons to be benefited or likely to be affected by execution of such special works ; and

(e) any other information as may be required by the licensing authority.

(3) The application shall also be accompanied by appropriate plans, drawings and specification containing information in regard to the execution of special works.

(4) On receipt of the application, the licensing authority (in case of licensing authority not being the Government) shall examine the proposal and submit the same alongwith its recommendations thereon to the Authority for approval.

(5) Where the licensing authority is the Government, it may forward the application received under sub-section (2) to the Authority for its opinion and specific recommendation.

(6) The Authority may seek such further information with respect to or in clarification of any aspect of the proposal submitted to it under sub-section (4) or forwarded to it under sub-section (5) from the licensing authority, as the Authority may think fit.

(7) On approval of the proposal by the Authority under sub-section (4) or on receipt of recommendations of the Authority under sub-section (5), the licensing authority shall grant permission for execution of special works.
Section 110 Powers and functions of the licensing authority and the authorised officer.
(1) For carrying into effect the provisions of this Chapter, the licensing authority or any officer authorised by it, shall have the following powers and functions, namely :––

(a) to enter any land, premises, unit or area, without notice during day time for making any investigation, inquiry, inspection or examination to ensure that the provisions of the Act are not contravened ;

(b) to require the licensee to execute, fix, remove, replace, renew, substitute, alter, repair, clean or examine any plant, equipment, machinery or work ;

(c) to take account of the quantity of water allocated and used for ensuring that the water used is in accordance with the quantity allocated or permitted in the terms of a licence, permit or any other authorisation under the Act ;

(d) to regulate the supply of water under a licence, permit or any other authorisation under the Act ;

(e) to take all steps and do all such acts as are necessary for––

(i) the purpose of taking measurements and making records of usage of the natural water resources ;

(ii) the conservation and regulation of water ;

(iii) the prevention of undue, excessive, illegal or improper use, diversion or waste of water ;

(iv) the preservation of water from pollution ; and

(v) the protection of and prevention of interference with the bed, banks, channels or other hydraulic works over or within which the water flows or is contained ;

(f) to use such force as may be necessary in the exercise of the powers and performance of the functions and duties conferred by or under the Act ;

(g) to take all steps and do all such acts and things as are necessary in the exercise of the powers and performance of the functions and duties conferred by or imposed under the Act;

(h) to exercise such other powers and perform such other functions and duties as the Government may by notification may specify.

(2) The power conferred by this section includes the power to break open the door of any premises where sinking of well or extraction/use of ground water may be going on :

Provided that the power to break open the door shall be exercised only after the owner or any other person in occupation of the premises, if he is present therein, refuses to open the door on being called to do so.

(3) The provisions of the Code of Criminal Procedure, Samvat 1989 shall, so far as may be, apply to any search or seizure under this section as they apply to any search or seizure made under the authority of a warrant issued under the said Code.
Section 111 Notification of areas to regulate and control development of ground water.
(1) If the Authority is of the opinion that it is necessary or expedient in the public interest to control, and/or regulate, the extraction or the use of groundwater in any form in any area, it may advise the Government to notify the area for the purposes of the Act with effect from such date as may be specified therein. On receipt of such advice, the Government may issue a notification to this effect :

Provided that the date so specified in the notification shall not be earlier than three months from the date of publication of the said notification.

(2) Every notification shall, in addition to its publication in the Government Gazette, be published in at least one daily regional language newspaper having wide circulation in the State and also be served in such manner as the Government may think fit and all or any of the following modes may be followed in affecting such service, namely :––

(a) by affixing a copy of the notification at some conspicuous part of the local body located in the said area ; and

(b) in such other manner as may be specified.

(3) If in the opinion of the Authority, the availability of the ground water has improved in a notified area, it may advise the Government to de-notify such area and the Government may do so in accordance with the procedure as may be prescribed in this behalf.

(4) The Authority shall also take steps to ensure that exploitation of ground water resources does not exceed the natural replenishment to the aquifers and wherever there is a mismatch, steps shall be taken to ensure augmentation of ground water resources in addition to regulatory measures.

(5) The Authority shall maintain and upkeep the data-base on ground water related information.
Section 112 Grant of permit to extract and use ground water in the notified area.
(1) Any user of ground water desiring to sink a well in the notified area for any purpose, either on personal or community basis, shall apply to the prescribed authority for grant of a permit for this purpose, and shall not proceed with any activity connected with such sinking unless a permit has been granted by such authority :

Provided that such user shall not have to obtain a permit if the well is proposed to be fitted with a hand operated manual pump or water is proposed to be withdrawn by manual devices.

(2) Every application under sub-section (1) shall be made in such form and shall contain such particulars as may be specified.

(3) On receipt of an application under sub-section (1) if the prescribed authority is satisfied that it shall not be against public interest to do so, it may, subject to such conditions and restrictions as may be specified, grant a permit authorizing the extraction and use of the water but where it is satisfied that it is not in public interest to do so, it may refuse to grant any such permission :

Provided that no person shall be refused a permit unless he has been given an opportunity of being heard.

(4) The decision regarding the grant or refusal of the permit shall be intimated by the prescribed authority to the applicant within a period of 90 days from the receipt of the application :

Provided that where the prescribed authority fails to communicate its decision within the said period, it shall be deemed that the permission has been granted.

(5) In granting or refusing a permit under sub-section (3), prescribed the authority shall have regard to the––

(a) purpose for which water is to be used ;

(b) existence of other competitive users ;

(c) availability of ground water ;

(d) quantity of ground water to be drawn ;

(e) quality of ground water with reference to use ;

(f) spacing of ground water structures keeping in consideration the purpose for which water is to be used ;

(g) long term behaviour of ground water level ;

(h) likelihood of adversely affecting water availability of any drinking water source in its vicinity ; and

(i) any other factor relevant thereto.

(6) The permit shall be in such form as may be prescribed.
Section 113 Duties, obligations and respon-sibilities of user agency/owner of a well.
(1) Every person or agency desiring to sink a well shall––

(a) inform the prescribed authority by at least 15 days prior notice in writing about his intension to do so ;

(b) erect a signboard on commencement of work near the well site indicating complete address of the user agency or the owner of the well and the drilling agency employed to sink the well ;

(c) erect barbed wire fencing or any other suitable barrier around the well during execution of work ;

(d) construct a concrete platform measuring 0.5 x 0.5 x 0.6 metre (0.3 metre below ground level and 0.3 metre above ground level) around the well casing ;

(e) cap the well assembly by welding steel plates or with nuts and bolts.

(2) On completion of work, such person or agency shall fill up the mud pits or channels and restore the ground condition to the position as existed before commencement of drilling operations or sinking of the well.

(3) If any user agency or owner of a well abandons such well, he shall fill up the abandoned well with clay, sand, boulders, pebbles or such other material from the bottom of such well to the ground level and obtain a certificate from the Executive Engineer concerned that such abandoned well has been properly filled up and capped.
Section 114 Registration of existing users in notified areas.
(1) Every existing user of ground water in the areas notified under sub-section (1) of section 111, shall within a period of one hundred twenty days from the date of notification, apply to the prescribed authority for grant of a Certificate of Registration recognizing its existing use in such form and in such manner as may be prescribed :

Provided that the prescribed authority may entertain any such application after the expiry of the said period of one hundred twenty days, if it is satisfied that the user was prevented by sufficient cause from submitting application in time :

Provided further that the existing user shall not be required to apply for registration if the existing well is fitted with a hand operated manual pump or water is withdrawn by manual device.

(2) The details to be furnished in an application under sub-section (1) shall include the following, namely :––

(a) the description of the source of ground water, such as type of well, its exact location ;

(b) the lifting device used ;

(c) the quantity of ground water, withdrawal and hours of operation per day ;

(d) the total period of use in each year ;

(e) the purpose for which ground water is being extracted ;

(f) in case of irrigation well, the location and extent of area likely to be irrigated ; and

(g) the details of the services involved in addition to the quantities of ground water extracted, the diversion or the pumping points and their location.

(3) On receipt of an application under sub-section (1), if the prescribed authority is satisfied that it shall not be against the public interest to do so, it may grant, subject to such conditions and restrictions as may be specified, a Certificate of Registration authorizing the continued use of the water or refuse to grant such Certificate :

Provided that no person shall be refused a Certificate of Registration unless he has been given an opportunity of being heard.

(4) The decision regarding the grant or refusal of the Certificate of Registration shall be intimated by the prescribed authority to the applicant within a period of ninety days from the receipt of the application :

Provided that where the prescribed authority fails to communicate decision within the said period, it shall be deemed that the Certificate of Registration has been granted.

(5) In granting or refusing a Certificate of Registration under sub-section (3), the authority shall have regard to the factors specified under sub-section (5) of section 112.

(6) The Certificates of Registration shall be in such form as may be prescribed.

(7) Pending communication by the prescribed authority of the decision on an application under sub-section (1), every existing user of ground water in the area notified under sub-section (1) of section 111 shall be entitled to continued use of the ground water in the same manner and to the same quantity as he was entitled prior to the date of his application.

(8) If a registered well becomes defunct, this fact shall immediately be brought to the notice of the prescribed authority by the user of ground water.
Section 115 Registration of user of new wells in non-notified area.
From the commencement of the Act, all wells sunk in the State shall be registered including the wells in the areas not notified under sub-section (1) of section 111, except those excluded under clause (zzj) of section 2 or brought to the notice of prescribed authority.
Section 116 Registration of Drilling Agencies.
(1) Every drilling agency, whether owned by the Government or any local body or a private individual, shall register itself with the prescribed authority in such manner as may be prescribed.

(2) Every owner or operator of a drilling agency shall follow the instructions issued by the prescribed authority from time to time.
Section 117 Power to alter, amend or vary the terms of the permit or Certificate of Registration.
At any time after a permit or Certificate of Registration, as the case may be, is granted, the prescribed authority may, for technical reasons, alter, amend or vary the terms of the permit or Certificate of Registration, as the case may be :

Provided the user of ground water shall be given an opportunity of being heard before issuance of any such order :

Provided further that before taking such action, the prescribed authority shall ensure that the standing crops are not damaged.
Section 118 Cancellation of permit or Certificate of Registration.
If the prescribed authority is satisfied either on a reference made to it in this behalf or otherwise, that––

(a) the holder of a permit or Certificate of Registration granted, under sub-section (3) of section 112, or sub-section (3) of section 114, has, without reasonable cause, failed to comply with the conditions subject to which the permit or Certificate of Registration has been granted or has contravened any of the provisions of the Act or the rules made thereunder ; or

(b) a situation has arisen which warrants limiting the use or extraction of ground water,

it may, without prejudice to any other penalty to which the holder of the permit or of the Certificate of Registration may be liable under the Act, after giving such holder an opportunity to show cause, cancel , alter or modify the permit or Certificate of Registration, as the case may be.
Section 119 Power to enter, inspect or seize etc.
(1) The prescribed authority or any person authorized by it in writing in this behalf, shall have the power to––

(a) enter on any property (private or government owned) with the right to investigate and make any measurements concerning the land or the water located on surface or underground ;

(b) inspect the well which has been or is being sunk and the soils and other materials excavated therefrom ;

(c) take specimen of such soils or other materials or of water extracted from such wells ;

(d) require by order in writing the persons sinking a well to keep and preserve in the prescribed manner specimens of soils or any material excavated therefrom for such period not exceeding three months from the date of completion or abandonment of the work, as may be specified by the prescribed authority or the person so authorised, as the case may be and thereupon such person shall comply with such requisition ;

(e) inspect and to take copies of the relevant record or documents and ask any question necessary for obtaining any information (including diameter or depth of the well which is being or has been sunk; the level at which the water is or was stuck and subsequently restored/ rested, the types of strata encountered in the sinking of the well and the quality of the water stuck) required for carrying out the purposes of the Act ;

(f) require, by order in writing, the user of ground water to install water measuring device on any ground water extraction structures :

Provided that where the user of ground water does not comply with the requisition issued to him within a period of sixty days, the prescribed authority itself may install such water measuring device and the cost so incurred shall be recoverable from the defaulting user of ground water as arrears of land revenue ;

(g) seize any equipment/device utilized for illegal sinking and destroy the work executed fully or partly ;

(h) require, by order in writing, any user of ground water who does not comply with the provisions of the Act and rules framed thereunder to close down the extraction of ground water or destroy any hydraulic work found to be illegal according to the provisions of the Act or the rules framed there under :

Provided that where the user of ground water does not comply with the requisition issued to him within a period of sixty days, the prescribed authority itself may carry out the necessary work and recover the cost from the illegal user of ground water as arrears of land revenue ;

(i) enter and search with such assistance, as it considers necessary, any place in which it has reason to believe that offence under the Act has been, or is being, committed and, direct by an order in writing, the person who has been, or is, committing the offence not to extract or use the ground water from a specified period not exceeding thirty days ;

(j) exercise such other powers as may be necessary for carrying out the purposes of the Act or the rules made hereunder.

(2) The power conferred by this section includes the power to break open the door of any premises where sinking of well or extraction/use of ground water may be going on :

Provided that the power to break open the door shall be exercised only after the owner or any other person in occupation of the premises, if he is present therein, refuses to open the door on being called to do so :

Provided further that if any such place is an apartment in the actual occupancy of a woman who, according to custom, does not appear in public, such officer shall, before entering such apartment, give notice to such woman that she is at liberty to withdraw and shall afford her every reasonable facility for withdrawing, and may then enter the apartment.

(3) The provisions of the Code of Criminal Procedure, Samvat 1989 shall, so far as may be, apply to any search or seizure under this section as they apply to any search or seizure made under the authority of a warrant issued under the said Code.
Section 120 Service of orders, etc.
(1) Every order issued under sub-section (1) of section 119 shall be served,––

(a) by giving or tendering the order or by sending it by post to the user for whom it is intended, or

(b) if such user cannot be found,––

(i) by affixing the order on some conspicuous part of his last known place of residence or place of business, or

(ii) by giving or tendering the order to some adult male member of his family, or

(iii) by causing it to be affixed on some conspicuous part of the land or building in which the well is being sunk.